PROJECT PROGRESS Block B

Development of Block B Project

Development of Block B Project

-Workshop equipment, including: fencing the land (project fencing); purchasing, installing and establishing a 60-ton weighbridge, and 20-ton, 16-ton and 12-ton tower cranes; purchasing required machineries, including loader, dump truck, etc. ; purchasing temporary electricity for the workshop; selecting and concluding the contract of consultation phase 3 and established laboratory; and concluding contract with different contractors.

-Land leveling operations for implementing foundation and deep foundation operations.

-Complete construction of in situ concrete piles and sandy pillars.

-Complete concreting.

-Complete foundation operations.

-Complete construction and installation of a metal skeleton.

-Construction of the shear wall and ceiling until 20thfloor.

-Framing of internal walls – under implementation.

-Construction of the metal skeleton of central lobby.

-Construction of the concrete ceiling and shear walls of central lobby.

-Construction and complete installation of the metal skeleton in central lobby.

-Complete construction of the concrete ceiling and shear walls of central lobby.

-Complete construction of the metal skeleton of elevators in central lobby.

-Metal skeleton of northern and southern parking lots in central lobby – under implementation.